Railway Avenue Sewer Upgrade

Duchess, Alberta

completeWastewaterISF
Federal contribution
$123,510
Federal share33%

of $370.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Village of Duchess
Construction start
Nov 16, 2009(actual)
Construction end
Sep 12, 2011(actual)

Against the original forecast

  • Construction start6 months earlyforecast Jun 1, 2010