Rehabilitation Highway 627
Stony Plain Indian Reserve No. 135, Alberta
Federal contribution
$1.3M
$1,264,114
Federal share50%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Jun 30, 2010(actual)
- Construction end
- Oct 10, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jun 15, 2010
- Construction end3 weeks earlyforecast Oct 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28934 in the federal list. How to read these figures.