Road Resurfacing on Sturgeon River Bridge
Federal contribution
$194,246
Federal share44%
of $444.2K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
2010
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Jul 1, 2010(actual)
- Construction end
- Sep 30, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2010
- Construction end2 weeks earlyforecast Oct 15, 2010
Also in Sturgeon County
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28936 in the federal list. How to read these figures.