Back to projects

Wastewater Pumping Station

Rosemary, Alberta

completeWastewaterISF
Federal contribution
$47,540
Federal share32%

of $148.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 12 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Village of Rosemary
Construction start
Jun 25, 2010(actual)
Construction end
Mar 31, 2011(actual)