Trunk 2 (from Lakeland Road) - Major Collector Highway

Newville, Nova Scotia

completeHighways and RoadsISF
Federal contribution
$810,000
Federal share50%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Nova Scotia
Construction start
Aug 17, 2009(actual)
Construction end
Oct 8, 2009(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2009
  • Construction end3 weeks earlyforecast Oct 31, 2009

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28988 in the federal list. How to read these figures.