Highway 19 (Island Highway) - Sayward Area Resurfacing
Federal contribution
$1.7M
$1,734,313
Federal share50%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedJan 25, 2010
2010
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Apr 12, 2010(actual)
- Construction end
- Oct 31, 2010(actual)
Against the original forecast
- Construction start2 months earlyforecast Jun 15, 2010
- Construction end4 weeks lateforecast Sep 30, 2010
Also in Sayward
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28989 in the federal list. How to read these figures.