Highway 14 - Metchosin to Sooke

Metchosin, British Columbia

completeHighways and RoadsISF
Federal contribution
$2.7M
$2,700,000
Federal share50%

of $5.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedJan 25, 2010
20102011
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Sep 8, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction end7 months earlyforecast Oct 31, 2011

Also in Metchosin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29001 in the federal list. How to read these figures.