Highway 97 Resurfacing
Federal contribution
$1.4M
$1,350,000
Federal share50%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedJan 25, 2010
2010
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Sep 18, 2009(actual)
- Construction end
- Nov 1, 2010(actual)
Against the original forecast
- Construction end2 weeks lateforecast Oct 15, 2010
Also in Falkland