Highway 97 Resurfacing

Falkland, British Columbia

completeHighways and RoadsISF
Federal contribution
$1.4M
$1,350,000
Federal share50%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedJan 25, 2010
2010
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Sep 18, 2009(actual)
Construction end
Nov 1, 2010(actual)

Against the original forecast

  • Construction end2 weeks lateforecast Oct 15, 2010

Also in Falkland

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29018 in the federal list. How to read these figures.