Back to projects

Cape Chignecto Provincial Park

West Advocate, Nova Scotia

completeRecreationISF
Federal contribution
$150,000
Federal share50%

of $300.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Nova Scotia
Construction start
Aug 1, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start8 months earlyforecast Apr 1, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29031 in the federal list. How to read these figures.