Highway 111 Improvements

Taschereau, Quebec

completeHighways and RoadsISF
Federal contribution
$2.3M
$2,302,239
Federal share50%

of $4.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jul 19, 2010(actual)
Construction end
Sep 16, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 30, 2010
  • Construction end2 weeks earlyforecast Sep 30, 2010