Highway 388 Improvements
Federal contribution
$1.9M
$1,893,500
Federal share49%
of $3.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Sep 7, 2010(actual)
- Construction end
- Jul 15, 2011(actual)
Against the original forecast
- Construction end4 months earlyforecast Oct 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29061 in the federal list. How to read these figures.