Back to projects

Trunk 7 (Sherbrooke) - Major Collector Highway

Sherbrooke, Nova Scotia

completeHighways and RoadsISF
Federal contribution
$1.9M
$1,890,000
Federal share50%

of $3.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 30, 2009
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Nova Scotia
Construction start
Aug 20, 2009(actual)
Construction end
Nov 5, 2009(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2009

Also in Sherbrooke