Widening of Highway 138
Federal contribution
$2.9M
$2,850,000
Federal share50%
of $5.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Nov 1, 2010(actual)
- Construction end
- Jul 27, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Oct 15, 2010
- Construction end5 weeks earlyforecast Aug 30, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29088 in the federal list. How to read these figures.