Heritage Park and Trail Construction
Summerside, Prince Edward Island
Federal contribution
$310,000
Federal share33%
of $930.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 4, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Summerside
- Construction start
- Aug 31, 2009(actual)
- Construction end
- Nov 30, 2010(actual)
Also in Summerside
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29125 in the federal list. How to read these figures.