Port and Terminal Expansion
Federal contribution
$26.4M
$26,400,000
Federal share44%
of $59.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedJul 28, 2010
20102011
Built
Approved 14 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Belledune Port Authority
- Construction start
- Aug 17, 2009(actual)
- Construction end
- Aug 31, 2011(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jul 1, 2009
- Construction end5 months lateforecast Mar 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29143 in the federal list. How to read these figures.