Back to projects

Highway 112 Repairs

Saint-Césaire, Quebec

completeHighways and RoadsISF
Federal contribution
$1.3M
$1,315,000
Federal share50%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jun 1, 2010(actual)
Construction end
Jul 26, 2010(actual)

Against the original forecast

  • Construction end3 months earlyforecast Oct 31, 2010

Also in Saint-Césaire

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29165 in the federal list. How to read these figures.