Eastbound Highway 10 at Marieville and Ste-Angèle-de-Monnoir
Federal contribution
$2.2M
$2,175,092
Federal share24%
of $9.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Aug 16, 2010(actual)
- Construction end
- Oct 18, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jul 1, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29176 in the federal list. How to read these figures.