Highway 20 Improvements
Federal contribution
$733,570
Federal share37%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Aug 16, 2010(actual)
- Construction end
- Sep 16, 2010(actual)
Against the original forecast
- Construction start11 months lateforecast Sep 1, 2009
- Construction end6 weeks earlyforecast Oct 31, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29227 in the federal list. How to read these figures.