Highway 117 Resurfacing

Réservoir-Dozois, Quebec

completeHighways and RoadsISF
Federal contribution
$3.6M
$3,600,000
Federal share50%

of $7.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Oct 19, 2010(actual)
Construction end
Aug 19, 2011(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Sep 1, 2010
  • Construction end2 months earlyforecast Oct 31, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29234 in the federal list. How to read these figures.