Highway 132 Repairs
Federal contribution
$1.1M
$1,056,348
Federal share44%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Jun 14, 2010(actual)
- Construction end
- Oct 31, 2010(actual)
Against the original forecast
- Construction end4 weeks lateforecast Sep 30, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29246 in the federal list. How to read these figures.