Bridge Replacements on Wilson Creek Forest Service Road

Slocan Lake, British Columbia

completeHighways and RoadsISF
Federal contribution
$223,250
Federal share48%

of $462.7K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 7, 2009
ApprovedJan 28, 2010
20102011
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 1, 2010(actual)
Construction end
Dec 20, 2010(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Sep 15, 2010
  • Construction end3 months lateforecast Sep 30, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29299 in the federal list. How to read these figures.