Bridge Replacement on St. Marys Forest Service Road
Federal contribution
$68,000
Federal share47%
of $143.5K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedJan 28, 2010
2010
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Oct 15, 2010(actual)
- Construction end
- Nov 12, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Sep 30, 2010
- Construction end5 weeks earlyforecast Dec 20, 2010
Also in Kimberley
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29302 in the federal list. How to read these figures.