Back to projects

Highway 20 Eastbound Resurfacing

Notre-Dame-du-Bon-Conseil, Quebec

completeHighways and RoadsISF
Federal contribution
$1.5M
$1,479,046
Federal share48%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jul 12, 2010(actual)
Construction end
Aug 14, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 14, 2010
  • Construction end7 weeks earlyforecast Sep 30, 2010

Also in Notre-Dame-du-Bon-Conseil