NWT Broadband Infrastructure Phase II

Yellowknife, Northwest Territories

completeBroadband And ConnectivityCSIF
Federal contribution
$14.8M
$14,814,120
Federal share50%

of $29.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 8, 2009
20092011201320152017
Built

Approved 2 weeks before the announcement.

Program
Canada Strategic Infrastructure Fund
Construction start
Apr 1, 2012(actual)
Construction end
Sep 30, 2017(actual)

Against the original forecast

  • Construction end18 months lateforecast Mar 31, 2016

Also in Yellowknife

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29334 in the federal list. How to read these figures.