In-Shuck-Ch Forest Service Road Improvements
In-SHUCK-ch Nation, British Columbia
Federal contribution
$301,500
Federal share50%
of $603.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedJan 28, 2010
20102011
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Nov 3, 2009(actual)
- Construction end
- Mar 11, 2011(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2009
- Construction end3 weeks earlyforecast Mar 31, 2011
Also in In-SHUCK-ch Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29339 in the federal list. How to read these figures.