River Trail

Revelstoke, British Columbia

completeActive TransportationISF
Federal contribution
$24,983
Federal share25%

of $99.9K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 13, 2009
ApprovedAug 10, 2009
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Revelstoke
Construction start
Oct 31, 2009(actual)
Construction end
Nov 30, 2009(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 1, 2009
  • Construction end4 months earlyforecast Mar 31, 2010