Langruth Water Treatment Plant Upgrades
Federal contribution
$178,318
Federal share33%
of $535.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Rural Municipality of Lakeview
- Construction start
- Nov 30, 2009(actual)
- Construction end
- May 25, 2011(actual)
Against the original forecast
- Construction end4 months earlyforecast Sep 30, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29449 in the federal list. How to read these figures.