Back to projects

Highway 339 Asphalt Repair

Saint-Roch-de-l'Achigan, Quebec

completeHighways and RoadsISF
Federal contribution
$915,601
Federal share41%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Aug 1, 2010(actual)
Construction end
Jun 23, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 1, 2010
  • Construction end2 weeks earlyforecast Jul 8, 2011

Also in Saint-Roch-de-l'Achigan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29459 in the federal list. How to read these figures.