Back to projects

Trans-Canada Highway - Highway 1 Paving (Provincial Road 340 to Provincial Road 351)

Douglas, Manitoba

completeHighways and RoadsISF
Federal contribution
$2.3M
$2,250,000
Federal share50%

of $4.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 22, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Manitoba
Construction start
Sep 20, 2009(actual)
Construction end
Nov 5, 2010(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 1, 2009

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29517 in the federal list. How to read these figures.