Back to projects

Birds Hill Bike Path Paving

Pine Ridge, Manitoba

completeActive TransportationISF
Federal contribution
$350,000
Federal share50%

of $700.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 22, 2009
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Manitoba
Construction start
Jun 22, 2009(actual)
Construction end
Oct 31, 2009(actual)

Against the original forecast

  • Construction end8 months earlyforecast Jun 30, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29523 in the federal list. How to read these figures.