Nutimik Facilities Modernization - Whiteshell Provincial Park
Federal contribution
$300,000
Federal share50%
of $600.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 22, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Manitoba
- Construction start
- Sep 16, 2009(actual)
- Construction end
- Aug 15, 2010(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Oct 1, 2009
- Construction end4 weeks lateforecast Jul 15, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29527 in the federal list. How to read these figures.