Improvement of Signage and Infrastructure on the Montréal/Delson-Candiac Commuter Train Line
Delson-Candiac-Sainte-Catherine, Quebec
Federal contribution
$330,178
Federal share35%
of $940.6K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011201220132014
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Jan 18, 2010(actual)
- Construction end
- Oct 31, 2013(actual)
Against the original forecast
- Construction start15 months earlyforecast Apr 21, 2011
- Construction end8 months earlyforecast Jun 30, 2014
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29535 in the federal list. How to read these figures.