Back to projects

Upgrading installations suppling drinking water at Morin Lake

Sainte-Marcelline-de-Kildare, Quebec

completeDrinking WaterCC
Federal contribution
$283,910
Federal share24%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 13, 2010
2010
Built

Approved 11 months before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Aug 1, 2009(actual)
Construction end
Sep 30, 2010(actual)