Back to projects

Wastewater treatment in the Landry Park sector

Saint-Jacques-le-Mineur, Quebec

completeWastewaterCC
Federal contribution
$461,762
Federal share42%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.6 years before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Oct 1, 2011(actual)
Construction end
Feb 1, 2016(actual)

Against the original forecast

  • Construction start16 months lateforecast Jun 1, 2010
  • Construction end5.3 years lateforecast Sep 30, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29551 in the federal list. How to read these figures.