Bridge Replacement on Aberdeen-Haddo Forest Service Road
Lake Country, British Columbia
Federal contribution
$53,358
Federal share47%
of $113.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedJan 28, 2010
2010
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Jul 15, 2010(actual)
- Construction end
- Sep 10, 2010(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Sep 1, 2010
- Construction end7 weeks earlyforecast Oct 30, 2010
Also in Lake Country
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29559 in the federal list. How to read these figures.