Improvements to Harrison West Forest Service Road
Port Douglas, British Columbia
Federal contribution
$420,000
Federal share50%
of $840.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedApr 7, 2009
ApprovedJan 28, 2010
20102011
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Oct 23, 2009(actual)
- Construction end
- Feb 4, 2011(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2009
- Construction end8 weeks earlyforecast Mar 31, 2011
Also in Port Douglas
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29570 in the federal list. How to read these figures.