Rebuilding On-ramps on Highway 210
Federal contribution
$1.1M
$1,050,618
Federal share47%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- May 31, 2010(actual)
- Construction end
- Jun 15, 2011(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Jun 15, 2010