Road Construction of Rural Road 32

Reciprocity No. 32, Saskatchewan

completeHighways and RoadsISF
Federal contribution
$255,000
Federal share33%

of $765.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 24, 2009
ApprovedJan 27, 2010
2010
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Saskatchewan
Construction start
Sep 5, 2009(actual)
Construction end
Nov 27, 2009(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jul 15, 2009
  • Construction end5 weeks earlyforecast Dec 31, 2009

Also in Reciprocity No. 32

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29641 in the federal list. How to read these figures.