Road Construction of Rural Road 32
Reciprocity No. 32, Saskatchewan
Federal contribution
$255,000
Federal share33%
of $765.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJan 27, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Sep 5, 2009(actual)
- Construction end
- Nov 27, 2009(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jul 15, 2009
- Construction end5 weeks earlyforecast Dec 31, 2009