Installation of Two Railway Yard Shelters
Federal contribution
$2.9M
$2,862,067
Federal share35%
of $8.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010201120122013
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Oct 5, 2009(actual)
- Construction end
- Dec 31, 2012(actual)
Against the original forecast
- Construction start5 weeks lateforecast Sep 1, 2009
- Construction end3.4 years earlyforecast May 31, 2016
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29651 in the federal list. How to read these figures.