Construction of Rural Road 252
Arm River No. 252, Saskatchewan
Federal contribution
$112,898
Federal share23%
of $485.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJan 27, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Sep 22, 2009(actual)
- Construction end
- Sep 28, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 15, 2009
- Construction end5 months earlyforecast Mar 1, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29652 in the federal list. How to read these figures.