Rosemor Industrial Park Road Improvements
Federal contribution
$109,469
Federal share29%
of $374.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 11, 2009
ApprovedJan 26, 2010
2010
Built
Approved 5 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Rural Municipality of Morris
- Construction start
- Jun 15, 2010(actual)
- Construction end
- Aug 20, 2010(actual)
Against the original forecast
- Construction end5 weeks lateforecast Jul 15, 2010
Also in Morris
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29653 in the federal list. How to read these figures.