Pavement Repairs on Highway 132

Percé, Quebec

completeHighways and RoadsISF
Federal contribution
$765,141
Federal share35%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Aug 2, 2010(actual)
Construction end
Oct 14, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 5, 2010
  • Construction end6 weeks lateforecast Sep 1, 2010

Also in Percé

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29695 in the federal list. How to read these figures.