Expansion and renovation of community centre and recreation cottage

Saint-Blaise-sur-Richelieu, Quebec

completeRecreationCC
Federal contribution
$446,703
Federal share32%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 2, 2009
201020112012
Built

Approved 8 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Sep 1, 2010(actual)
Construction end
Mar 31, 2012(actual)

Against the original forecast

  • Construction end14 months lateforecast Jan 31, 2011

Also in Saint-Blaise-sur-Richelieu

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29806 in the federal list. How to read these figures.