Toronto-York Spadina Subway Extension

Toronto, Ontario

completePublic TransitMIC
Federal contribution
$622.0M
$621,999,637
Federal share27%

of $2.3B total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 5, 2008
20092011201320152017
Built

Approved 3 months before the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
Nov 27, 2009(actual)
Construction end
Mar 15, 2018(actual)

Against the original forecast

  • Construction end4 months earlyforecast Jun 30, 2018