Infrastructure work along Principale Street

Cowansville, Quebec

completeWastewaterCC
Federal contribution
$1.2M
$1,211,681
Federal share33%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 8, 2009
2010201220142016
Built

Approved 3 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Cowansville
Construction start
Oct 29, 2014(actual)
Construction end
Nov 30, 2016(actual)

Against the original forecast

  • Construction start5.1 years lateforecast Sep 4, 2009
  • Construction end5.2 years lateforecast Oct 6, 2011

Also in Cowansville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29859 in the federal list. How to read these figures.