Updating the water treatment system in Shawinigan
Federal contribution
$24.0M
$24,030,048
Federal share37%
of $64.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 7, 2014
2014201720202023
BuiltForecast
Approved 4 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- City of Shawinigan
- Construction start
- Jun 13, 2016(actual)
- Construction end
- Dec 31, 2024(forecast)
Against the original forecast
- Construction start3 weeks earlyforecast Jul 1, 2016
Also in Shawinigan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29874 in the federal list. How to read these figures.