Halton Region Wastewater Treatment (Skyway Facility)

Burlington, Ontario

completeWastewaterGIF
Federal contribution
$51.4M
$51,429,057
Federal share32%

of $158.9M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedNov 6, 2009
ApprovedMar 18, 2010
201020112012201320142015
Built

Approved 4 months after the announcement.

Program
Green Infrastructure Fund
Construction start
Mar 2, 2012(actual)
Construction end
Sep 1, 2015(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Apr 10, 2012
  • Construction end2.8 years earlyforecast Jun 30, 2018

Also in Burlington

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29893 in the federal list. How to read these figures.