Montreal Réno-Systèmes Phase 3
Federal contribution
$149.7M
$149,700,000
Federal share33%
of $455.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 26, 2013
20102013201620192022
BuiltForecast
Approved 2.7 years before the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Société de transport de Montréal (STM)
- Construction start
- Jul 12, 2011(actual)
- Construction end
- Mar 31, 2023(forecast)