Beverly Street Improvement
Federal contribution
$16,371
Federal share33%
of $49.1K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Eby-Grenfell Local Roads Board
- Construction start
- Dec 1, 2009(actual)
- Construction end
- Sep 30, 2010(actual)
Against the original forecast
- Construction end4 weeks lateforecast Aug 31, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 29960 in the federal list. How to read these figures.