Dresden Storm Sewers
Federal contribution
$1.0M
$1,000,000
Federal share33%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Chatham-Kent
- Construction start
- Nov 7, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start5 months earlyforecast Apr 1, 2010
- Construction end4 weeks lateforecast Sep 30, 2011
Also in Dresden